Single-Record Projections Updates not working as the release notes state.

The release notes state that the single projection update ability is for projection codes OR phase/cost type.  But, when you click calculate after highlighting the phase/cost type, all of the phase/cost type update, along with the projection code.

Steps to reproduce

Enter a date and project
Find or create a Projection Code with multiple Phases/Cost Types
Run a Projection with Plugged Values and process.

Go back into the PM Cost Projection
Enter the same project
Highlight a plugged value phase/cost type
select the calculate button
change to Always Calculate
and process

Current results

All of the phases/cost types become un-plugged and have recalculated.  The projection code has also re-calculated.

Expected results

The release notes state that the Phase/Cost Type can be calculated on a single-record.

  • Andrew Karr
  • Mar 9 2017
  • In Review
Company Kraus Anderson
Job Title / Role PM
I need it... Yesterday...Come on already
  • Attach files
  • Guest commented
    May 05, 2020 03:48

    Please provide what you said you provided (but did not) only that was 3 years ago. Come on already.

  • Mark Faller commented
    May 01, 2020 18:42

    Your user experience score will be significantly enhance when you finally get this done!

  • Dave Deutschman commented
    May 01, 2020 14:19

    This would be used in conjunction for clearing the plugged value for the Phase code. It is not uncommon to have over 300 Phase Codes and as many as 50 plugged values on our Jobs. If a Project Manager wants to remove the plugged value and recalculate a single Phase code, they have to clear all plugs, recalculate the cost projection, add the other plugs back into the projection, and recalculate.

    To keep track of the plugs, our PMs are adding them to the notes . This is adding a lot of time to the creation of a cost projection.

Dear Viewpoint Suggestion Box contributor;

We at Viewpoint sincerely thank you for your contribution to Suggestion Box on how we can improve Viewpoint products. While we can’t do everything at once, we rely upon your feedback to help guide the prioritization of our product improvements, and Suggestion Box is a critical tool for us to understand and prioritize our customers’ needs. Viewpoint reviews Suggestion Box regularly for all of our products and updates statuses, adds comments, and performs various house-keeping (including deleting) as needed to ensure that Suggestion Box is maintained as a productive environment for product enhancements requests.

1515 SE Water Avenue, Suite 300, Portland, OR 97214 |  800.333.3197  | Contact Us | Terms of Use | Privacy | Support Policies

© 2023 Trimble Inc. All Rights Reserved. Viewpoint®, Vista™, Spectrum®, ProContractor™, Jobpac Connect™, Viewpoint Team™, Viewpoint Analytics™, Viewpoint Field View™, Viewpoint Estimating™, Viewpoint For Projects™, Viewpoint HR Management™, Viewpoint Field Management™, Viewpoint Financial Controls™, Vista Field Service™, Spectrum Service Tech™, ViewpointOne™, ProjectSight® and Trimble Construction One™ are trademarks or registered trademarks of Trimble Inc. or its affiliates in the United States and other countries. Other names and brands may be claimed as the property of others.