Submit Your Suggestions for Vista

Ideaspace topics with the most votes have been moved into the Suggestion Box. If there is a topic missing, please re-enter. Our product team reviews the Suggestion Box items regularly and will provide updates as to status and incorporation into upcoming releases.

Fix Remaining Committed Cost on a PO to be actual, not forced based on the PO tax rate.

Remaining Committed Cost should be the Total Committed Cost for a PO minus the Actual Cost of the Invoice(s).

Currently any report (PM Contract Analysis Drilldown, PO Drilldown, PO Purchase Order Status Report) that shows Remaining Committed Cost/Remaining Cost on a PO will be inaccurate if the invoiced tax is different than the tax rate on the PO.  This is because when an invoice is posted, it will take the invoice amount, ignore the tax entered during AP Entry, and apply the tax rate that is on the PO when it is pushed over to JC committed cost.  Remaining Committed Cost should be the Total Committed Cost for a PO minus the Actual Cost of the Invoice.  If Vista forces the PO tax rate onto the invoice, it will show in all reports with a $0 Remaining Committed and project managers will have no idea that the invoice does not match the PO unless they open the invoice. The fact that AP Unapproved Invoice Review doesn't show any information on the PO, PO tax $ or tax rate makes it extremely difficult to catch any tax discrepancies during invoice approval.  The PM needs to know that there is a discrepancy so either the PO or invoice can be corrected.

Example:

PO Entry- Amount $100/ Tax $10 = $110

AP Entry (Actual Invoice)- Invoice $100/ Tax $8 = $108

Remaining Committed should be $2, instead, in the PM Contract Analysis Drilldown for example, it is showing as $0 because it will show:

Total Cmtd Cost $110

AP Entry           -$110 (instead of the $108 it actually is because Vista has forced the PO tax)

Remaining Cost $0

  • Breanna Signore
  • Jul 27 2018
Company MMC Contractors
Job Title / Role Project Manager
I need it... Yesterday...Come on already
  • Attach files

Dear Viewpoint Suggestion Box contributor;

We at Viewpoint sincerely thank you for your contribution to Suggestion Box on how we can improve Viewpoint products. While we can’t do everything at once, we rely upon your feedback to help guide the prioritization of our product improvements, and Suggestion Box is a critical tool for us to understand and prioritize our customers’ needs. Viewpoint reviews Suggestion Box regularly for all of our products and updates statuses, adds comments, and performs various house-keeping (including deleting) as needed to ensure that Suggestion Box is maintained as a productive environment for product enhancements requests.

1515 SE Water Avenue, Suite 300, Portland, OR 97214 |  800.333.3197  | Contact Us | Terms of Use | Privacy | Support Policies

© 2023 Trimble Inc. All Rights Reserved. Viewpoint®, Vista™, Spectrum®, ProContractor™, Jobpac Connect™, Viewpoint Team™, Viewpoint Analytics™, Viewpoint Field View™, Viewpoint Estimating™, Viewpoint For Projects™, Viewpoint HR Management™, Viewpoint Field Management™, Viewpoint Financial Controls™, Vista Field Service™, Spectrum Service Tech™, ViewpointOne™, ProjectSight® and Trimble Construction One™ are trademarks or registered trademarks of Trimble Inc. or its affiliates in the United States and other countries. Other names and brands may be claimed as the property of others.